Construction update – Jubilee Place

Construction of Jubilee Place is continuing apace and on-schedule. The structure will top out in July 2021, with the unique steel diagrid form now installed to level 8 and jumping another 4 floors as part of the next lift to level 12.

The services fit out is now complete from the basement through level 3 and the façade installation has commenced on the lower levels giving a glimpse of the final visual form of the building as it begins to take shape. 

In the foyers and lower levels, the mechanical louvres that will draw air in through the lower levels are now being installed, creating cross-ventilation to ensure a quality environment for all occupants.

Works on the refurbishment of the heritage listed Jubilee Hotel will start in the June quarter and are timed to be complete along with the Jubilee Place commercial building by the end of 2021.